Article 6. Electricity
15-601 Application for Service.
That all persons desiring to use electric current shall file an application with the City Clerk.
(Ord. 357; Code 2019)
15-602 Reserved.
(Ord. 357; Ord. 640; Code 2019)
15-603 Equipment to be Installed by City.
City shall furnish normal installation facilities including meters and all such equipment, facilities, meters and connections shall be accessible to City’s authorized inspector for the purpose of inspection, testing and adjusting when deemed desirable by said inspector.
(Ord. 357; Code 2019)
15-604 Inspection.
All connections, wiring, facilities and equipment shall be inspected by City’s authorized Inspector prior to customer receiving service and at such other times as are consistent with the provisions of this article. Said connections, wiring, facilities and equipment shall be installed and maintained at all times in conformity with the requirements of the National Board of Fire Underwriters and with the National Code.
(Ord. 357; Code 2019)
15-605 Underground Service.
Resident home owners may request and receive with approval of the City, underground distribution of service. Customer shall provide at his own expense the necessary facilities for receiving such underground service, including the difference in installation costs of overhead and underground service.
(Ord. 357; Code 2019)
15-606 Rates.
Electric current shall be furnished to residential and commercial users at such rates and charges which shall be from time to time fixed by the City Council, and which shall be at all times sufficient in the aggregate to provide revenues for the payment of all operating costs and all other costs and charges incidental to the operation by the city of the electrical current system.
(Ord. 357; Ord. 378; Code 2019)
15-607 Reserved.
(Ord. 357; Ord. 640; Code 2019)
15-608 Tampering; penalty.
That any person or persons tampering with a meter or wiring in any manner to avoiding payment of the regular rates shall be deemed guilty of a misdemeanor, and upon conviction be fined in an amount of not more than $500.00.
(Ord. 357; Ord. 391; Code 2019)
15-609 Unlawful transfer or diversion of electric current.
(Ord. 708)
15-610 Interconnection standards for customer-owned generation facilities.
There is hereby adopted Interconnection Standards for Installation and Parallel Operation of Customer-Owned Renewable Electric Generation Facilities Dated August 18, 2025.
(Ord. 723; Ord. 731)